Bond Update - August 5, 2015




Quick Starts

Blackburn, Morton, Lewis & Clark, Marrs, North, Area C Package #1 – These projects are near completion with the remaining construction work to be phased and completed this fall.

Ponca - Temporary Classrooms (Portables) – Final inspections schedule for this week.  

Ponca - Selective demolition has started with construction to be complete in February 2016.

 

Group 1

Belle Ryan and Western Hill – Selection of the CM@R has been completed, the Board of Education approved Sampson Construction to perform these services.  Educational Specification has been approved and Schematic Design documents will be submitted to the Board of Education for approval in the Fall of 2015.   

Indian Hill – Selection of the CM@R has been completed, the Board of Education approved Lund-Ross Constructors to perform these services.  Schematic Design documents have been approved and Design Development documents will be submitted to the Board of Education in the Fall of 2015.  

Northwest – Selection a CM@R is scheduled for next month.  Educational Specifications have been approved and Schematic Design documents are schedule to be submitted to the Board of Education in the Fall of 2015.  

Crestridge & Sunny Slope - Educational Specification has been approved and Schematic Design documents are schedule to be submitted to the Board of Education in the Fall of 2015. 

 

Group 2

Florence – Educational Specification has been approved and Schematic Design documents are schedule to be submitted to the Board of Education in the Fall of 2015. 

Lothrop & Joslyn – Educational Specification has been approved and Schematic Design documents are schedule to be submitted to the Board of Education in the Fall of 2015. 

JP Lord – Design firm selection was approved by the Board of Education.  BCDM will provide design services.  Educational Specification documents will be submitted to the Board of Education in the Fall of 2015. 

 

Group 3

Beveridge –  Selection of a CM@R is scheduled for next month.  Educational Specifications documents are scheduled to be submitted to the Board of Education in the Fall of 2015. 

South & Central – Schematic Design documents scheduled to be submitted to the Board of Education in the Fall of 2015.  

Rest of Group 3 projects in design work for Educational  Specifications this Fall.

 

Group 4

Architectural selection of these projects is scheduled for the beginning of 2016, with construction scheduled to starting the Fall of 2016.

Bond Update - June 2, 2015

 

Bond Update - June 2, 2015

Quick Start Projects:

                Several projects have been bid out and on-site construction activities have commenced. 

                Ponca Elementary School will be issued for bid on June 08, 2015.

               

Group 1 Projects:

All Educational Specification packages are scheduled to be presented to the Board of Education during the month of June.

Group 2 Projects:

                Architectural Selection for JP Lord will be completed in June 2015 with a recommendation presented to the Board of Education in July 2015.                

Educational Specification is on-going at Florence, Joslyn and Lothrop.     

 

Group 3 Projects:

                Architectural Selection for all Group 3 projects have been completed; recommendation will be presented to the Board of Education on June 15, 2015.    

                Educational Specification Committee meetings will commence in June 2015.


Economic Inclusion:

The first class of the Jacobs Construction Academy was held on June 02, 2015.    

 


Bond Update - April 6th, 2015

Current Major Activities Update
Received Construction Manager at Risk Statement of Qualification (SOQ) and Proposals for Ponca Elementary School, evaluation of SOQs and Proposals will occur next.     
Quickstart Projects - Construction bids for Marrs, Blackburn, Picotte, Prairie Wind and Fullerton (Planning Area C Package 1) are scheduled to be received on April 14 and 16, 2015.
Group 1 Projects* - Educational Specifications Committee meetings continue.  Negotiation of Architect Agreements on-going.   
Group 2 Projects** - Educational Specifications Committee meetings continue.  Negotiation of Architect Agreements on-going. 
Economic Inclusion - Meeting with construction contractors that have shown interest in bidding on 2014 Bond construction projects.     
 
*Group 1 Projects:
Capital Improvements – Northwest High School, Crestridge and Indian Hill Elementary Schools 
‘Open Plan’ Schools – Franklin and Sunny Slope Elementary Schools 
Replacement Schools – Belle Ryan and Western Hills Elementary Schools
 
**Group 2 Projects:
Capital Improvements – Florence Elementary School
‘Open Plan’ Schools – Lothrop and Joslyn Elementary Schools